North Sydney Olympic Pool Redevelopment in Milsons Point Delayed Amid Cost Disputes

The completion of the North Sydney Olympic Pool redevelopment in Milsons Point has been pushed back to June 2025, with ongoing disputes over cost variations. 



Initially scheduled for completion in mid-2024, the project continues to face delays, primarily due to issues surrounding the structural steel roof over the 25-metre indoor pool.

Project Background and Delays

North Sydney Olympic Pool
Photo Credit: NSC/YouTube

The North Sydney Olympic Pool, a historic swimming facility located at Milsons Point, has been undergoing redevelopment since March 2021. Originally set to reopen in 2023, the project has faced multiple setbacks, with its timeline now extending 11 months beyond the revised July 2024 completion target.

The latest delay is attributed to complications involving the structural steel roof over the 25-metre indoor pool, which has been a point of contention between the NSC and contractor Icon. Cost disputes related to rectification work on the roof have resulted in mediation and adjudication, with some claims being ruled against.

Since December 2024, Icon has submitted four new Extension of Time (EoT) claims, of which three were rejected by the authorities, while the fourth remains under assessment.

Financial Impact and Cost Variations

The total forecast cost for the redevelopment remains at $122 million. However, as the project nears completion, additional variation claims are expected.

The revised construction contract sum is $91.74 million, with $173,000 in newly approved variations. Confidential discussions are ongoing regarding further cost adjustments, as authorities continue to evaluate the financial implications of unresolved claims.

Construction Progress and Current Status

Despite the delays, several key milestones have been reached:

  • Structural Steel Ramp Completion: The Eastern Stair Tower ramp is now in place, improving accessibility for wheelchair users and prams.
  • Gelato Bar & Sundeck: The Level 2 gelato bar and sundeck structure are nearing completion, with the final paving set to be installed.
  • Amenities & Tiling: Underfloor heating and tiling in Level 1 changerooms are finished, and waterproofing has been completed for Level 1 amenities. Level 3 is next in line for similar work.
  • Internet Cabling: The facility’s internet infrastructure has been connected, preparing the site for operational readiness.

Community Sentiment and Next Steps

Local officials have emphasised that their priority remains delivering a high-quality facility. However, ongoing construction delays and cost disputes have drawn criticism from residents and stakeholders.



Once construction is complete, an additional three months will be required for commissioning and site preparation before the facility officially opens. Authorities have stated they will continue monitoring project developments and providing regular updates.

Published 26-Feb-2025